used open space for something a little different today. Building a 35 story high rise currently we are framed with drywall top out done up to level 09 with layout done up to L19. MEP subs having layout of penetrations through walls on time is almost always an issue with “go backs” by framer/drywaller trade usually associated with missing layout. Sequencing has the MEP trades laying out their penetrations 1 floor ahead of framing.
This creates opportunity for an openspace capture right before framing begins that accounts for layout having been present at the time framing begins and eliminates argument of weather layout was or was not there. This helps greatly with identifying cost responsible party of said “go back” work.
Held camera face down towards floor about waist height with a decent light and walked the entire floor, every wall line and defiantly captured what was or was not there at the time.
PRICELESS!